Projects Department has started the work of the Project of :
( Qurainat , PWD Project . ph.2 E-house HVAC System Completion Works ) on Wednesday , 24 / July / 2019 for Rumaila Operating Organization – ROO in South Rumaila Oil Field:

Activities as follows but not limited to :
# Brazing all tubes connections between units ,

# Cleaning the tubes by Freon R11 ,

# Pressure Leak Test and drying by N2 ,

# Vacuum of all system tubing ,

# Charging with Freon R 410 A ( NOT sure if the condenser units filled with Freon R 410 A , we will check during the work ) ,

# Completion of insulation of jointing points ( Materials put in this CTR – Foster Coating considered , other insulation materials are available in site ) ,

# Pipe supports ( concrete blocks will be supplied by ROO ) ,

# fit up, joint preparation, soldering, pressure/leak testing, purging and charging with approved refrigerant gas of the refrigerant piping (cooper).